Centro Oeste Aqueduct Construction.
Santa Fe - Argentina
Excavation p/foundations: 325,000 m3. Soil filling: 244.900 m3. Concrete: p/Elem. Pre-molded: 854 m3. Concrete structures: 8.560 m3. Plant water treatment capacity: 242 I/sec. The intake work, precast concrete viaduct to 250 m of length and loading chamber. Construction of 17 cisterns: from 500 to 5,000 m3. 4 pumping stations. Supply and installation of 19 pumps. Hydraulic capacity: EST. forklift intake work: 0, 26m 3/s. EST. forklift, plant output: 0,242m 3. 4 Dump Tanks. GRP pipes: Ø500 mm: Ø33.390m. Ø450 mm: Ø45.000m. Ø315 mm: Ø49.615m. Plumbing PVC class 6: Ø250 mm: 50.250m. Ø200 mm: 4.450m. Ø160 mm: 51.860m. Reduction valves, drains, air and pressure sustaining valves: 370 pcs. Casing Ø Variables 610/305 mm for crossing roads, railways, canals and streams: 1180 meters and laying of 25 km of medium voltage line. SCADA control system.